WOL only works immediately never as planned or cron task
-
r946 should now have scheduled tasks back. Hopefully this helps, but please test. I don’t know what Imageable.interface.php was supposed to have so I haven’t a clue as to where to begin coding this if it was truly ever needed in the first place.
-
I’ve since, I think, fixed this issue and will post the updates. I’ve also added the tools to start viewing the scheduled jobs as nothing was in place for this. When I have time tomorrow, I’ll try to upload my changes. Hope all is well. First file that needed changing is the one I already uploaded once. It didn’t work through my testing, but I narrowed how to get it sort of working, I think. Again, I have nothing much I can truly test on, but at least I can see the jobs trying to run.
-
r947 was out, please don’t try was testing something and forgot to remove those tests.
r948 is out and should have scheduled tasks back though I don’t really know for sure. Please test.
-
I am adding the caveat to this, as reading a little further, you’re stating that this bug was with 0.32 and I have been updating 0.33. I still don’t know if the jobs are working properly, but can see what’s going on in 0.32. Maybe I’ll have another aha moment when looking into this for you all.
I’m not familiar with scheduled tasks too much beyond crontab specified, so if my results aren’t working fully yet, I’m very sorry.
-
I’m about to release another revision due to Scheduled tasks. Again it’s only for 0.33, but it seems to, finally, be working properly. *'s work just like crontab. There’s a couple other issues in scheduling the task that’s a little off, but that’s validation problems and not scheduling problems.
I’ve only tested using false values for everything and watching log files. Real-world I haven’t a clue, but at least I can say with some assurance it appears to be working as expected. I haven’t figure out the Single Scheduled task entry process yet and haven’t tested it because of this reason. So to be blatant, only cron style tasks seem to be working for now.
Hopefully this helps.
-
I think I actually got it through more rigorous checking with my test system. It actually looks to create the task as active in wait for the job to start.
-
Told ya he’d get it
-
Yep, Not quite a million updates, but a lot of frustrating testing.
Again, I don’t have any thing real to test with, but I can watch the tasks being activated, and verify they’re now activating when they’re expected to. Hopefully this is what’s needed. For the Task Run Time in the log viewer, I have the dates working to display the rfc time based on the timestamp for delayed jobs, and for cron jobs, it just displays the cron as is present on the database. It appears, so far, all is working properly now.
-
How do I get 0.33?
-
You can download from SVN with:
[code]svn co https://svn.code.sf.net/p/freeghost/code/trunk fog_0.33b[/code] then cd to the fog_0.33b folder and perform normal install or you can download a pre-made tarball at latest revision with:
[url]https://mastacontrola.com/fog_0.33b.tar.bz2[/url]Extract the tarball with:
[code]tar -xjf fog_0.33b.tar.bz2[/code]Then cd into the fog_0.33b folder and perform normal install from there.